2012 Bond Issue

2012 Bond Projects
RIO RANCHO HIGH SCHOOL
Interior Improvements ($500,000) Partial B-Box Lighting  Complete
HVAC Upgrade (2,000,000)  Complete
Stadium Improvements ($350,000)  Complete 
Baseball Field Turf (outfield) ($500,000)  Complete 
Horseshoe Landscaping/Parking ($250,000)  Complete 
Perimeter Wall ($100,000)  Complete 
Baseball Field Lighting ($350,000)  Complete 
Soccer Field Lighting ($250,000)  Complete 
IT Infrastructure Upgrades  Mostly Complete
   
V. SUE CLEVELAND HIGH SCHOOL
East Event Parking Addition ($200,000)  Complete 
Baseball Field Lighting ($200,000)  Complete 
Softball Lighting ($200,000)  Complete 
Landscaping ($180,000)
 Planning
   
INDEPENDENCE HIGH SCHOOL
IT Infrastructure Upgrades  Complete
New Roof ($300,000)  Complete 
Exterior Improvements  Design complete, construction 
  anticipated in Summer 2018
   
RIO RANCHO MIDDLE SCHOOL
HVAC Improvements (Gym) ($500,000)  Complete
New Track ($250,000) Reassigned to CHS/RRHS track improvements  Complete
Link Glazing Improvements ($100,000)  Complete 
IT Infrastructure Upgrades  Mostly Complete;
 Fire alarm upgrade in process
   
EAGLE RIDGE MIDDLE SCHOOL
HVAC Improvements ($1,200,000)  Complete
Tennis Courts ($150,000)  Complete 
IT Infrastructure Upgrades  Fire alarm and intercom
 upgrades in process 
   
MOUNTAIN VIEW MIDDLE SCHOOL
IT Infrastructure Upgrades   Mostly Complete; 
 Fire alarm upgrade in process
Tennis Courts ($150,000)  Complete 
HVAC Improvements  ($1,200,000)   Complete
   
LINCOLN MIDDLE SCHOOL (final phase of 2012 bond)
Interior Renovation ($1,450,000)  In design, construction anticipated Summer 2018
Electrical Upgrade ($500,000)  Related to interior renovations
Track Improvements ($200,000) Reassigned to CHS/RRHS  Complete
Kitchen Equipment Upgrade ($200,000)  In Design  
New Gym ($3,000,000)  Bid awarded, contract being executed,
 construction begins late December 2017
 or January 2018
Window Replacement ($400,000)  Related to interior renovations
Upgrade HVAC system ($1,500,000)  In design
   
CIELO AZUL ELEMENTARY
Landscaping Improvements ($75,000)  Planning
Electronic Access (FOB) ($50,000)  In Design  
Security System Upgrades  $45,000
   
COLINAS DEL NORTE ELEMENTARY
IT Infrastructure Upgrades  Complete
Window Replacement ($200,000)  Complete 
HVAC Upgrade ($1,200,000)  Complete
   
ERNEST STAPLETON ELEMENTARY
Electronic Access (FOB) ($50,000)  Complete 
Security System Upgrades  Pricing
IT Infrastructure Upgrades  Cabling for portables in process
   
ENCHANTED HILLS ELEMENTARY
HVAC Upgrade ($1,500,000)  Complete
IT Infrastructure Upgrades  In process
   
MAGGIE CORDOVA ELEMENTARY
Site Landscaping ($100,000)  Complete 
Parking Lot Expansion ($250,000)  Complete 
Security System Upgrades ($30,000)  Complete 
Electronic Access (FOB) ($50,000)  Complete 
IT Infrastructure Upgrades  Phones and Intercom in process
   
MLK ELEMENTARY
Parking Lot Improvements ($200,000)  Complete 
New HVAC ($1,100,000)  Planning
   
PUESTA DEL SOL ELEMENTARY
Window Replacement ($250,000)  Complete 
Electronic Access (FOB) ($50,000)  Complete 
Cafeteria Wall Modification ($150,000)  Complete
Security System Upgrades ($45,000)  Complete
IT Infrastructure Upgrades  Mostly Complete
   
RIO RANCHO ELEMENTARY 
HVAC Upgrade (Annex) ($1,300,000)  Complete
Roof Replacement (Annex/Gym) ($1,500,000)  Complete
IT Infrastructure Upgrades  Fire alarm and intercom
 upgrades in process  
   
SANDIA VISTA ELEMENTARY
Overflow Parking Lot ($300,000)  In construction
Landscaping ($100,000)  Planning
Electronic Access (FOB)  $50,000
Security System Upgrades  $30,000
   
VISTA GRANDE ELEMENTARY
IT Infrastructure Upgrades  Complete
Security System Upgrades  $40,000
Classroom Addition ($4,700,000)  Complete
   
SHINING STARS PRESCHOOL
Note: Some projects deferred due to pending design/construction of new campus
Classroom Renovation ($400,000)  Complete 
HVAC Upgrades ($250,000)  Deferred
Site Lighting ($200,000)  Deferred
Landscaping ($100,000)  Complete 
Parking Lot Improvements ($200,000)  Complete/some funds deferred
IT Infrastructure Upgrades  Phone and network improvements in process
   
JOE HARRIS ELEMENTARY ($10,000,000)
This project was included in the 2012 bond with completion contingent on receipt of state matching funds and provision of sufficient operational funding to the district as was fully disclosed to voters.  Due to the continuing unavailability of funds the project was deferred, with the funding reallocated by the school board to assure full completion (as opposed to phasing) of other voter-approved projects in the 2012 bond: the Vista Grande classroom wing, the Lincoln Middle School gym, and the transportation center. 
   
TRANSPORTATION (final phase of 2012 bond)
New Transportation Center ($2,400,000+) Under construction, estimated completion Spring 2018
   
REAL ESTATE
Land Purchase ($3,506,000)   In Progress 
   
DISTRICT WIDE PROJECTS
Softball Complex Lighting ($400,000)  Complete 
Softball Complex Turf ($400,000)  Complete 
   
DISTRICT OFFICE
HVAC Upgrade ($200,000)  Complete
Interior Improvements ($165,000)  Complete
IT Infrastructure Upgrades  Mostly Complete
   
Total: $50,000,000