2007 Bond Issue

2007 Bond Projects
Note:  Some funds from the 2007 bond designated for school construction were re-purposed (reallocated) by the school board when matching funds to complete new schools were not forthcoming from the state and operational budgets were cut during the recession.  See the 2007 Bond Reallocation Projects list for details on these projects. 
Cleveland High School Phase II: additional matching funds, athletics, facilities, auxiliary gym, concert hall, technology and furnishings ($32,997,587)  Complete 
Sandia Vista Elementary - additional matching  funds, technology, and furnishings (1,602,055)  Complete 
Cielo Azul Elementary: matching funds, furnishings, and technology ($7,059,261)  Complete 
Joe Harris Elementary: matching funds, furnishings, and technology ($9,741,218)  Design completed/construction deferred due to lack of state matching funds, reduction in assessed valuation/tax collections, and unavailability of operational funds for opening 
New Middle School ($14,150,000)  Educational specifications partially completed/design on hold and construction deferred due to lack of state matching funds, reduction in assessed valuation/tax collections, and unavailability of operational funds for opening 
Data/Cabling Infrastructure Upgrades ($140,000)  Complete 
Audio Visual/Cable Infrastructure Upgrades ($270,000)  Complete 
Master Planning ($210,000)  Complete 
Real Estate Acquisition/contingency ($16,072,879)  Ongoing/some contingency funds reallocated to Phase II facilities at Cleveland High 
Warehouse ($2,500,000)  Complete 
Bond Sale Administrative Costs ($400,000)  Complete 
   
RIO RANCHO HIGH SCHOOL
Fine Arts Academy - Black Box Construction ($1,500,000)  Complete 
Culinary Arts Improvements ($200,000)  Complete 
Football Stadium Expansion (amended to turf replacement) ($1,000,000)  Complete 
Bleacher Improvements ($1,000,000)  Complete 
Wrestling Room Expansion ($400,000)  Complete 
Soccer Field/ Athletics Training Center ($2,000,000)  Complete 
   
INDEPENDENCE HIGH SCHOOL*
New Building Design (amended to upgrades at Quantum campus) ($500,000)  Complete 
   
RIO RANCHO MID-HIGH SCHOOL (Now Rio Rancho Middle School)
Program Enhancements  Deferred when district could not move forward with New Tech High concept (state funding crunch) 
Canopy on Plaza ($75,000)  Complete 
Track/All Weather  Deferred due to decision to build 
 Cleveland HS
Parking Drainage Improvements ($300,000)  Complete 
   
EAGLE RIDGE MID-SCHOOL
Landscape ($100,000)  Complete 
Telecom Upgrade ($40,000)  Complete 
Roofing ($300,000)  Complete 
Exterior Bldg. Improvements ($400,000)  Complete 
Track ($200,000)  Complete 
   
MOUNTAIN VIEW MID-SCHOOL
Replace carpeting ($100,000)  Complete 
Telecom Upgrade ($40,000)  Complete 
Roofing ($300,000)  Complete 
Exterior Building improvements ($200,000)  Complete 
Retaining Walls ($200,000)  Complete 
   
LINCOLN MID-SCHOOL
Replace the Bleachers ($250,000)  Complete 
Interior Upgrades ($150,000)  Complete 
Telecom Upgrade ($40,000)  Complete 
Exterior Lighting/Improvements ($100,000)  Complete 
New Roof ($250,000)  Complete 
Replace floor tiles ($200,000)  Complete 
Upgrade HVAC system ($100,000)  Ongoing 
   
COLINAS DEL NORTE E.S.
Playground Upgrade ($100,000)  Complete 
Kitchen/Cafeteria Expansion ($1,000,000)  Complete 
Exterior Improvements ($100,000)  Complete 
Site Fencing ($75,000)  Complete 
   
 ERNEST STAPLETON E.S.
Landscaping/Field (outdoor classroom) ($200,000)  Complete 
   
ENCHANTED HILLS E.S.
Site Improvements (BELOW K-Garten) ($200,000)  Complete 
Complete HVAC Controls Upgrade ($100,000)  Complete 
Parking Drainage Improvements ($200,000)  Complete 
   
MAGGIE CORDOVA E.S.
Site landscaping ($100,000)  Complete 
Field Installation ($200,000)  Complete 
   
MARTIN LUTHER KING E.S.
Phase 4 Administration Renovation ($1,400,000)  Complete 
New HVAC ($300,000)  Ongoing 
Improve Playground ($50,000)  Complete 
   
PUESTA  E.S. 
Extend Parking Lot ($200,000)  Complete 
Telecom Upgrade ($40,000)  Ongoing 
Drop Off Improvements ($100,000)  Complete 
   
RIO RANCHO E.S.
Exterior Improvements ($100,000)  Complete 
Interior Improvements ($100,000)  Complete 
Walking Track Upgrade ($100,000)  Complete 
   
VISTA GRANDE E.S.
Playground Equipment/Landscaping ($100,000)  Complete 
Classroom/core addition matching funds ($3,465,000)  Core addition received state matching funds and is completed. 
Classroom addition was not funded and deferred to the 2012 bond. 
   
SHINING STARS PRE-K
New Windows ($100,000)  Complete 
New Fire Alarm Upgrade ($100,000)  Complete 
Canopy Painting ($75,000)  Complete 
Administrative and campus access renovation  Complete 
   
Total:  $105,000,000 (approximately $18.4 million reallocated)