Lincoln Middle School Projects

Lincoln Middle School

2287 Lema Rd. SE

Project:  New Gymnasium

Scope of Work:  Design and construction of a new gymnasium to replace the old.  The existing gym will be used as an auxiliary gym and multi-purpose room.

Design Professional:  Van H. Gilbert Architect

Contractor:  TA Cole and Sons Construction

Start Date:  Design complete.  Project bid December 5, 2017, construction start January 4, 2018.

Anticipated Completion Date:  Winter 2019

Status Update:

Construction is well underway.  Concrete block continuing, steel erection in progress.  Project is moving on schedule and within budget.  No construction issues.


LMS Gym

Lincoln Middle School construction

Lincoln Gym


Project:‚Äč  Interior Improvements

Scope of Work:  Replacement of all rooftop mechanical units, replacement of ceiling tiles, replacement of interior fluorescent lighting with LED lighting.

Design Professional:  Van H. Gilbert Architect

Contractor:  Thompson Construction, Inc.

Start Date:  Design complete, project bid April 16, 2018.  Construction will start May 28, 2018.

Anticipated Completion Date:  Spring 2019

Status Update:  Project bid April 16, 2018.  Thompson Construction, Inc. was the successful bidder.  Currently in contract phase with construction scheduled to start week of May 28, 2018.