Lincoln Middle School Projects

Lincoln Middle School

2287 Lema Rd. SE

Project:  Gymnasium and Interior Improvements

Scope of Work:  Design and construct a new gymnasium; re-purpose old gym and auxiliary gym to classroom, media center and labs, replace mechanical units, plumbing and electrical upgrade to existing building.

Design Professional:  Van H. Gilbert Architect

Contractor:  TBD

Start Date:  Design prof. selection Aug 2014; Gym design complete Fall 2017; anticipated bid Fall 2017; construction start January 2018.  Interior Improvements design 80% complete, anticipated bid Winter 2018; construction start Spring to Summer 2018.

Anticipated Completion Date:  Gymnasium – Winter 2019; Interior Improvements – Summer 2019

Status Update:

Gymnasium and Interior Projects have been split into two separate projects being bid and construction separately.  The Gymnasium was advertised on October 29, 2017; Pre-bid conference on November 2, 2017; Bid opening on December 5, 2017; Board review on December 11, 2017.  Construction will take approximately 12 months to complete and must be accomplished prior to construction work on the existing school building (Interior Improvements).

Design documents on the Interior Improvements project are currently being reviewed/revised with an anticipated completion in Winter of 2018 and bidding in early Spring 2018.  The intent is to begin construction in the Summer of 2018.

LMS Gym